Analisis Perawatan pada Pipa Superheater di Unit Boiler 1 menggunakan Metode Risk Based Inspection
DOI:
https://doi.org/10.36706/jrm.v23i2.404Keywords:
Risk Based Inspection, Superheat pipe, Inspection schedule plan, risk levelAbstract
The failure of the superheat pipe is one of the important problems that often occur in steam power plants, this is caused by thinning on the surface due to abrasion by silica sand contained in the combustion gas flow continuously during operation. Based on the failures that occurred in the boiler pipes in the 3x10 MW TE unit, this is very risky and has a major effect on electricity production. In addition, this also causes considerable financial problems due to downtime. In this study, we used the risk-based inspection method to provide an overview of the inspection schedule plan. As a result, based on the API 581 standard, the probability of failure is category 5 and the financial risk is level C. Therefore, the risk level of the superheat is medium-high. Conditionally, we expect the power plant to run the inspection schedule 27 days after the failure report based on the thickness measurement.
Downloads
References
R. Rosihan, R. I., Puspitasari, D. P., & Rumita, “Penilaian Resiko dan Perencanaan Jadwal Inspeksi Boiler dengan Metode Risk Based Inspection di PT Indonesia Power UBP Semarang,” Industrial Engineering Online Journal, 2014. https://ejournal3.undip.ac.id/index.php/ieoj/article/view/5348 (accessed Aug. 03, 2023).
V. Wahyu Endriyana, “Analisa Unjuk Kerja Secondary Supeheater PLTGU Dan Evaluasi Peluang Peningkatan Effectiveness Dengan Cara Variasi Jarak, Jumlah, dan Diameter Tube,” J. Tek. ITS, vol. 2, no. 3, pp. B388–B393, 2013, doi: 10.12962/j23373539.v2i3.5114.
API 581, “Risk-based Inspection Technology, API RP 581 Second Edition,” no. September, p. 654, 2008.
O. H. octora syahida Rahman, F. W. Pratama, and E. S. Siradj, “Risk Indentification on Superheater Pipeline Boiler of 600 MW Power Plants Using a Risk Based Inspection (RBI) Method,” J. Pendidik. Teknol. Kejuru., vol. 5, no. 4, pp. 111–114, 2022, doi: 10.24036/jptk.v5i4.29523.
API 581, API RP 581 - THIRD EDITION, APRIL 2016 - Risk-Based Inspection Methodology, no. April. 2016.
A. K. Insani et al., ANALISIS RISIKO DAN PERENCANAAN JADWAL INSPEKSI PADA BOILER DAN PERALATAN PENDUKUNG BOILER DENGAN METODE RISK BASED INSPECTION ( RBI ). 2020.
T. Liu, T. Jiang, J. Zhong, K. Guan, Z. Wang, and F. Arjmand, “Failure analysis of sulphidation-oxidation corrosion of Incoloy 800HT superheater tube,” Eng. Fail. Anal., vol. 142, p. 106798, Dec. 2022, doi: 10.1016/J.ENGFAILANAL.2022.106798.
H. Muhajir, G. D. Haryadi, and A. Widodo, “Remaining Life Assessment of Superheater Tube in Boiler of Coal Fired Power Plant,” MATEC Web Conf., vol. 159, pp. 1–6, 2018, doi: 10.1051/matecconf/201815902041.
M. A. Qathafi and Sulistijono, “Studi Aplikasi Metode RBI semi-Kuatitatif API 581 pada Production Separator,” J. Tek. ITS, vol. 4, no. 1, pp. 89–94, 2015, doi: 10.12962/j23373539.v4i1.8722.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Jurnal Rekayasa Mesin
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Jurnal Rekayasa Mesin (JRM) memberikan akses terbuka terhadap siapapun agar informasi dan temuan pada artikel tersebut bermanfaat bagi semua orang. Semua konten artikel Jurnal ini dapat diakses dan diunduh secara gratis, tanpa dipungut biaya, sesuai dengan lisensi creative commons yang digunakan.